Building Rewire Schedule

Building

Communications Room Construction Status

Building rewire status
Migration Status
Estimated Completion Date
Johnson Sceince Tower
complete
complete
complete
Aug. 29, 2008
Bobby Chain Tech
complete
complete
in progress
Feb. 28, 2009
Walker Science
not started
not started
not started
TBD
Polymer Science
not started
not started
not started
TBD